Robust optimization for resource-constrained project scheduling with uncertain activity durations

Résumé

The purpose of this paper is to propose models for project scheduling when there is considerable uncertainty in the activity durations, to the extent that the decision maker cannot with confidence associate probabilities with the possible outcomes of a decision. Our modeling techniques stem from robust optimization, which is a theoretical framework that enables the decision maker to produce solutions that will have a reasonably good objective value under any likely input data scenario. We develop and implement a scenario-relaxation algorithm and a scenario-relaxation-based heuristic. The first algorithm produces optimal solutions but requires excessive running times even for medium-sized instances; the second algorithm produces high-quality solutions for medium-sized instances and outperforms two benchmark heuristics.
Fichier principal
Vignette du fichier
robustRCPSP-final-submitted.pdf (311.86 Ko) Télécharger le fichier
Origine : Fichiers produits par l'(les) auteur(s)
Loading...

Dates et versions

hal-00564435 , version 1 (08-02-2011)

Identifiants

Citer

Christian Artigues, Roel Leus, Fabrice Talla Nobibon. Robust optimization for resource-constrained project scheduling with uncertain activity durations. Flexible Services and Manufacturing Journal, 2013, 25 (1-2), pp.175-205. ⟨10.1007/s10696-012-9147-2⟩. ⟨hal-00564435⟩
157 Consultations
683 Téléchargements

Altmetric

Partager

Gmail Facebook X LinkedIn More